Saturday, March 14, 2009

3/15/09 Updated Pictures

This week has been trim, tile, and cabinet week.








Sunday, March 8, 2009

3/8/09 UPDATE

This week has been a busy week. All of the hardwood and most of the tile was laid. The stairs, railing, and banister was constucted. Finally, the exterior brick was finished.

Upstairs Banister
Staircase


Hardwood in master bedroom


Friday, February 20, 2009

Update 2/15/09

The exterior is almost finished. This week the siding was put on and painted.
The garage doors were installed.


Inside the sheetrock has been hung and mudded. This is a view from the upstairs balcony down into the great room.
This is looking from the great room to the upstairs balcony.
The siding on the rear has to be painted. Rear garage door was installed and the columns on the deck are half bricked.

Wednesday, February 4, 2009

February 4, 2009

As you can see the sheetrock has been hung. They are in the process of mudding and sanding. Hopefully, the sheetrock will be completely finished by the end of next week. The next stage will be laying the hardwood and tile. The cabinets should be ready by the time the flooring is finished.

Master Bedroom

Dining Room

Kitchen

Sunday, January 11, 2009

January 11, 2009

Almost finished with the brick! Electrical, plumbing, and heat/air are now complete. They are also finished with insulation and will begin sheetrocking this week.

Saturday, December 20, 2008

12/20-Update

A lot has happened on the inside of the house since the last post. All of the plumbing and electrical work is complete. The heating and air ducts are also installed. Last week they delivered the staircase and almost took out the front door in the process. Outside, the brickwork is about 70% complete and we have added our front door. The next phase will be the insulation followed by the sheetrocking which we hope to start after Christmas.






Thursday, December 4, 2008

Beating The Cold

The past 10 days we have been dealing with the cold weather. The brick layers have worked when weather has permitted. The right side of the house is now fully bricked and they are starting on the back. Tuesday, the electricians began the rough wiring and the plumber is suppose to start the rough plumbing any day.